Value: $1,590,937.87
Owner: North Harris County Regional Water Authority
Engineer of Record: AECOM

Project Overview

When the bonding company for BRH Garver needed a trusted partner to complete NHCRWA Project 25C, Reytec Construction was selected to step in and deliver the final scope with precision and accountability. The project involved the installation and testing of an 84-inch water line along the CenterPoint Energy Northbelt Corridor in north Houston.

Scope & Key Components

Reytec’s team executed a series of completion activities to bring the project to full closeout. Major work elements included:

  • Regrading and site restoration
  • Completion of the cathodic protection system
  • Installation of vault interior piping
  • Manhole adjustments and final alignments
  • Pressure testing and verification of system integrity

Challenges & Execution Approach

Taking over a partially completed project required detailed coordination, accurate assessment of prior work, and strict adherence to specifications. Reytec’s team applied thorough field verification, safety oversight, and continuous communication with the owner and engineer to ensure all deficiencies were resolved quickly and effectively.

Impact & Benefits

Completion of the project restored critical water transmission capacity to the North Harris County Regional Water Authority system, enhancing service reliability for surrounding communities and supporting future regional growth.

Demonstrating Reytec’s Expertise

This project reflects Reytec’s reputation for stepping in, solving complex challenges, and delivering critical infrastructure safely, efficiently, and to the highest standard.

By Published On: October 22nd, 2025Categories: WaterworksComments Off on NHCRWA Project 25C – 84” Water Line Along CenterPoint Energy Northbelt Corridor

Share This Story, Choose Your Platform!

Timeline

Categories