CALDER STREET DRAINING IMPROVEMENT PH I

Contract amount: $24 million Calder Street Drainage Improvement: This job included street and drainage improvements on Calder Street from Pheland Boulevard to the IH-10 east bound frontage road. The work included removing landscaping, planters, asphalt overlay, concrete pavement and curb, flexible base, surfacing, driveways and sidewalks. Reytec also removed inlets, manholes, culverts and storm

WILLIAMS ST.

Contract amount: $19 million Williams Drive Phase I & II from Rodd Field Road to Airline Drive: This included street and drainage improvements on Williams Drive. (The new drive became a main artery in Corpus Christi’s new medical district.) The work included installing large storm sewer boxes with a new outfall as well as all

By |2024-03-04T10:11:44+00:00January 15th, 2019|Heavy Civil Construction|

UT M.D. ANDERSON HERMAN PRESSLER ROAD PROJECT

Contract amount: $4.5 million M.D. Anderson Ambulatory Clinical Care Building – Herman Pressler Road & Utility Extension: Reytec acted as prime subcontractor to Hensel Phelps, a design build general contractor. This project included concrete and asphalt paving, curbs, sidewalks, storm sewer, domestic water, sanitary sewer and landscaping. We installed new, four-lane concrete boulevards of 25,000

By |2024-03-04T10:28:46+00:00January 15th, 2019|Heavy Civil Construction|

UPTOWN DEVELOPMENT AUTHORITY – MIDDLE SECTION

This construction included the removal of existing asphalt paving and curb for approximately 1,000 linear feet and the placement of 10-inch thick, 5-lane concrete boulevard section with 9-inch crushed subgrade.

By |2024-03-04T10:29:40+00:00January 15th, 2019|Heavy Civil Construction|

Neighborhood Street Reconstruction (NSR) No. 465

Contract amount: $15.3 million Neighborhood Street Reconstruction No. 465A: This job included the construction of paving, drainage, water and wastewater improvements along segments of various neighborhood streets throughout the Springwood Oaks, Timber Oaks, Wrenwood Oaks and Royal Oaks subdivisions in the Spring Branch area. For more details on this project, please contact Reytec Projects.

By |2024-03-04T10:36:19+00:00January 15th, 2019|Heavy Civil Construction|

HOUSTON RAPID TRANSIT EAST END PAVING

Contract amount: $3.1 million East End Utility Relocation Segment 1B: This included public utility relocations over a portion of the East Corridor along Harrisburg Boulevard between Stiles Street and Altic Boulevard. East End Paving This entailed construction of initial roadway construction for the East End Corridor between Everton Street and Stiles Street along Harrisburg Boulevard.

By |2024-03-04T10:39:42+00:00January 15th, 2019|Heavy Civil Construction|

KIRBY DRIVE STORM SEWER RELIEF PROJECT SEGMENT 3

Contract amount: $14.3 million Kirby Drive Storm Sewer Relief Project Segment 3: Reytec served as the prime contractor to the City of Houston and was responsible for the traffic control, street lighting, pavement markings, pollution prevention, site work/landscaping, demolition of existing concrete/asphalt and paving (curbs, sidewalks and storm sewer). This project consisted of: approximately 2,945

By |2024-03-04T10:44:13+00:00January 15th, 2019|Heavy Civil Construction|

THE UNIVERSITY OF TEXAS M.D. ANDERSON CANCER CENTER

Contract amount: $9 million U.T. Research Park Infrastructure Improvements Phase One: Reytec served as the prime subcontractor to J.E. Dunn, a design build general contractor. We were responsible for the turnkey installation of all utilities listed below. Underground Utilities: 4,461 linear feet of 12-inch PVC water main, open cut 952 linear feet of 8-inch PVC

By |2024-03-04T10:49:07+00:00January 15th, 2019|Heavy Civil Construction|

HEDRICK FORCE MAIN CROSSING

Contract amount: $ 2.9 million Hedrick Force Main Crossing: Our work for the City of Houston included the demolition and replacement of the existing aerial force main with underground 42-inch force main, crossing Buffalo Bayou at Wayside Drive and 69th Street. For more details on this project, please contact Reytec Projects.

By |2024-03-05T16:30:36+00:00January 14th, 2019|Waterworks|

Chaparral Street – Williams St. to Schatzel St.

Contract Amount: $5 million Downtown Street Improvements to Chaparral Street from William Street to Schatzel Street: This project included the redesign of the roadway and pedestrian right of way of Chaparral Street between William Street and Schatzel Street. The right of way included designed pavers, planters and catenary lighting to enhance the overall atmosphere of

By |2024-03-04T10:59:05+00:00January 14th, 2019|Heavy Civil Construction|